20 September 2024 | GMAT | QUANT

A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?

  • 60
  • 70
  • 75
  • 80
  • 100
0 voters